Captive & Group Captive Power Plants under Open Access

Overview

Open Access (OA) is a mechanism that allows large electricity consumers (typically those with demand greater than 1 MW) to buy power directly from independent power producers, such as solar or wind developers. Instead of relying solely on local DISCOMs, consumers can procure energy at competitive prices from the open market.

This model helps industries and commercial establishments lower their energy costs, hedge against rising grid tariffs, and gain access to renewable energy sources for achieving sustainability goals. The electricity is "wheeled" or transmitted through the existing transmission grid, ensuring reliable delivery to the consumer's location.


Structure & Legal Requirements

Governed by Electricity Rules, 2005 – Rule 3 (under Electricity Act, 2003)


Commercial Benefits

ItemCaptive / Group CaptiveNormal Grid Tariff
Energy Cost₹3.5 – ₹4.5 / unit (solar/wind mix)₹7 – ₹12 / unit
Savings30–50%
Tariff Stability25 years (PPA)DISCOM tariffs escalate annually
No Cross Subsidy Surcharge (CSS)
No Additional Surcharge (AS) if eligibility met
Banking allowed (varies by state)
Accelerated Depreciation benefit for equity holders

Suitable Consumers

Factories with high daytime usage
Large corporate campuses
Data centres, logistics parks, cold storages
Multiple SMEs under same group (Group Captive)

Key Setup Options

ModelDescriptionOwnership
Solar CaptiveGround-mounted 1 MW+ plant under OAConsumer
Wind CaptiveSuitable in windy states (e.g., TN, MH, KA)Consumer
Hybrid CaptiveWind + solar mix for 24×7 supplyConsumer / Group

Process Flow

01

Form SPV (Special Purpose Vehicle) for plant

02

Sign Shareholder Agreement & PPA

03

Apply for Open Access & Connectivity

04

Plant constructed (3–6 months typical)

05

Power wheeled to consumer through state grid

06

Monthly billing via SLDC / utility


Financial Snapshot — Illustrative (1 MW Solar Captive)

1 MW Solar Captive — Key Numbers

Project Cost₹4.5 Cr
Equity Needed (26%)₹1.17 Cr
Tariff₹4 / unit
Annual Generation~15 lakh units
Annual Savings₹60–75 lakh
Payback3–4 years

Captive / Group Captive Solar Plant under OPEX Model

Under the OPEX (Pay-as-you-go) model, a solar developer invests, installs, operates, and maintains the solar power plant. The consumer pays per unit of electricity (₹/kWh) through a long-term Power Purchase Agreement (PPA) — usually for 15–25 years.

What Makes It "Captive" Under OPEX?

RequirementCaptive / Group Captive Rule
Equity OwnershipConsumer must own ≥26% of the power plant / SPV
Power ConsumptionMust consume ≥51% of total power generated annually
Minimum LoadTypically ≥1 MW per consumer (varies by state)

In a Group Captive OPEX model, the developer funds the project but gives 26% equity stake to the consumer(s) at minimal or no cost, to meet legal compliance. Consumers pay only for energy used (e.g., ₹3.5–₹4.5/unit).

Hybrid OPEX + Captive Structure

StakeholderRole
Developer (RESCO / OPEX partner)Invests CapEx (~₹4–5 Cr/MW), builds & operates plant
Consumer (C&I Client)Takes 26% stake in SPV & signs long-term PPA
SPV (Special Purpose Vehicle)Owns the asset, enters into Open Access agreements

Commercial Snapshot — 1 MW Solar (Group Captive - OPEX)

Group Captive OPEX — Key Numbers

Project Cost₹4.5 Cr
Equity (26%)₹1.17 Cr (can be provided by developer on behalf of consumer)
PPA Rate₹3.5–₹4.5 / kWh
DISCOM Tariff₹8–₹12 / kWh
Annual Generation~15 lakh units
Savings₹60 lakh – ₹1 Cr / year
Tenure15–25 years

No CapEx burden on consumer + long-term energy cost savings.


Benefits to Consumer

Zero CapEx, 100% OPEX-based
Long-term tariff stability (no DISCOM hikes)
Bypass cross subsidy & additional surcharge
Green power = improved ESG rating
No O&M headache – fully handled by developer
Can be used for multiple sites (Group Captive)

Key Considerations

AspectNotes
EquitySome developers pass 26% stake to consumers at no cost or nominal share value
Compliance RiskIf consumer does not consume 51%, benefits are lost (must be monitored)
OA ChargesTransmission, wheeling, SLDC, banking, etc. – vary by state
AgreementLong-term PPA + Shareholding Agreement mandatory

Setup Timeframe

Feasibility & SPV Setup
~30 days
Approvals (SLDC, OA)
45–90 days
Construction
90–120 days
Total to Power Flow
~6 months
Scroll to Top